DefinitionA queue position reserves capacity, but the power actually available depends on grid works and reinforcements, sometimes in tranches, with possible operating limitations in between. The useful question is not "is the PTF signed?" but "which MW, and when?".

WHAT IS THE DIFFERENCE BETWEEN RESERVED AND FIRM CAPACITY?

It is the most expensive confusion in the sector: a site that is "connected" or "in the queue" does not necessarily have its power available. Before buying, leasing or financing, get the schedule of deliverable MW, step by step, and the conditions attached.