DefinitionOptional study delivered by RTE in about six weeks: a first view of feasibility, cost and timeline. It does not bind RTE and reserves no capacity. Read our article.

WHAT IS AN RTE EXPLORATORY STUDY FOR?

It tests a site before larger costs are committed: an order of magnitude for cost, timeline and grid works. Because it reserves no capacity, a seller presenting an exploratory study as a power guarantee is overstating the site. It replaces neither the PTF nor queue entry.