DefinitionReform of RTE's queue, consulted on in February 2026: capacity would be reallocated to the most advanced projects rather than the earliest ones. Expected to apply from 1 January 2027.
WHAT DOES "FIRST READY, FIRST SERVED" CHANGE?
If approved by the regulator CRE, the rule will give more weight to a file's maturity than to the date of the request: land control, permits under way, a credible schedule. As of mid-November 2026 the reform was not yet in force. Projects should prepare now the documents that prove their progress.
RELATED TERMS
- Queue entry : Requires the PTF specific conditions signed without reservation, proof of land control (a promise to sell is often enough at first), the first instalment, and evidence of project progress or a flat fee of €1,000 per MW.
- Annual review : Every year, on the anniversary of queue entry, the project must again prove progress (or pay the €1,000 per MW fee, at most twice) and, if land control rested on a promise, show it still holds it.
- Reserved versus firm capacity : A queue position reserves capacity, but the power actually available depends on grid works and reinforcements, sometimes in tranches, with possible operating limitations in between.
SAME TOPIC
Exploratory study · PTF · Connection agreement · Connection offer from Enedis
← The full grid connection glossary · Our sources