DefinitionEvery year, on the anniversary of queue entry, the project must again prove progress (or pay the €1,000 per MW fee, at most twice) and, if land control rested on a promise, show it still holds it.
WHAT HAPPENS AT THE ANNUAL QUEUE REVIEW?
The annual review is a deadline not to miss: a project that cannot show progress, or has lost its land, risks leaving the queue. It belongs in a deadline register, alongside land options and appeal periods.
RELATED TERMS
- Queue entry : Requires the PTF specific conditions signed without reservation, proof of land control (a promise to sell is often enough at first), the first instalment, and evidence of project progress or a flat fee of €1,000 per MW.
- Deadline register : A table tracking everything that can cost a project time or capacity: annual queue review, capacity steps, land option expiry, appeal periods, manufacturing slots.
- First ready, first served : Reform of RTE's queue, consulted on in February 2026: capacity would be reallocated to the most advanced projects rather than the earliest ones.
SAME TOPIC
Exploratory study · PTF · Connection agreement · Connection offer from Enedis · Reserved versus firm capacity
← The full grid connection glossary · Our sources
A PROJECT AFFECTED?
Our independent experts apply these notions to your file, with no commission and no brokerage. The expert: Xavier Watrelos.