DefinitionRTE's formal connection offer: solution, works, cost, indicative timeline. The project only enters the queue once the developer accepts it.
WHAT IS AN RTE PTF?
The PTF is the first document that truly commits: by accepting it, the project enters the queue and pays a first instalment. It should be read beyond the total cost: the technical solution, reinforcement works, the stepped schedule and validity conditions. An "indicative" schedule is not a guaranteed date.
RELATED TERMS
- Exploratory study (étude exploratoire) : Optional study delivered by RTE in about six weeks: a first view of feasibility, cost and timeline.
- Connection agreement (convention de raccordement) : The contract that follows the PTF: scope, cost, schedule and, where relevant, capacity steps.
- Queue entry : Requires the PTF specific conditions signed without reservation, proof of land control (a promise to sell is often enough at first), the first instalment, and evidence of project progress or a flat fee of €1,000 per MW.
SAME TOPIC
Annual review · First ready, first served · Connection offer from Enedis · Reserved versus firm capacity
← The full grid connection glossary · Our sources
A PROJECT AFFECTED?
Our independent experts apply these notions to your file, with no commission and no brokerage. The expert: Xavier Watrelos.