DefinitionRTE's formal connection offer: solution, works, cost, indicative timeline. The project only enters the queue once the developer accepts it.

WHAT IS AN RTE PTF?

The PTF is the first document that truly commits: by accepting it, the project enters the queue and pays a first instalment. It should be read beyond the total cost: the technical solution, reinforcement works, the stepped schedule and validity conditions. An "indicative" schedule is not a guaranteed date.