DefinitionThe date when the grid can actually deliver the project's target capacity, step by step. Neither the PTF date nor the end of construction: the pivot date of the schedule. See the Readiness Manager.

WHAT IS A PROJECT'S GRID DATE?

A project's whole schedule should start from this date: equipment orders, construction, leasing, financing. A misjudged grid date drags everything else, and it is often what a lender should check first.