DefinitionThe date when the grid can actually deliver the project's target capacity, step by step. Neither the PTF date nor the end of construction: the pivot date of the schedule. See the Readiness Manager.
WHAT IS A PROJECT'S GRID DATE?
A project's whole schedule should start from this date: equipment orders, construction, leasing, financing. A misjudged grid date drags everything else, and it is often what a lender should check first.
RELATED TERMS
- Grid-back schedule : A schedule built backwards from the grid date: land option duration, permit filings, equipment orders, consultation, financing, ramp-up.
- Reserved versus firm capacity : A queue position reserves capacity, but the power actually available depends on grid works and reinforcements, sometimes in tranches, with possible operating limitations in between.
- Time to Connect : Real time between a project decision and energisation.