DefinitionRequires the PTF specific conditions signed without reservation, proof of land control (a promise to sell is often enough at first), the first instalment, and evidence of project progress or a flat fee of €1,000 per MW.

HOW DOES A DATA CENTER ENTER RTE'S CONNECTION QUEUE?

Queue entry is when a project secures its place. It requires specific documents, and the file must then stay current: an expiring land option or a stalled project can cost the position. This is why land control and schedule are checked from the request onwards.