DefinitionRequires the PTF specific conditions signed without reservation, proof of land control (a promise to sell is often enough at first), the first instalment, and evidence of project progress or a flat fee of €1,000 per MW.
HOW DOES A DATA CENTER ENTER RTE'S CONNECTION QUEUE?
Queue entry is when a project secures its place. It requires specific documents, and the file must then stay current: an expiring land option or a stalled project can cost the position. This is why land control and schedule are checked from the request onwards.
RELATED TERMS
- Annual review : Every year, on the anniversary of queue entry, the project must again prove progress (or pay the €1,000 per MW fee, at most twice) and, if land control rested on a promise, show it still holds it.
- First ready, first served : Reform of RTE's queue, consulted on in February 2026: capacity would be reallocated to the most advanced projects rather than the earliest ones.
- PTF (proposition technique et financière) : RTE's formal connection offer: solution, works, cost, indicative timeline.
SAME TOPIC
Exploratory study · Connection agreement · Connection offer from Enedis · Reserved versus firm capacity
← The full grid connection glossary · Our sources
A PROJECT AFFECTED?
Our independent experts apply these notions to your file, with no commission and no brokerage. The expert: Xavier Watrelos.