DefinitionA table tracking everything that can cost a project time or capacity: annual queue review, capacity steps, land option expiry, appeal periods, manufacturing slots.
WHAT IS A DEADLINE REGISTER FOR?
A data center project rarely loses its place for a technical reason: it loses it on a missed deadline. The register brings every date that can cost time or capacity into one table, with an owner for each.
RELATED TERMS
- Annual review : Every year, on the anniversary of queue entry, the project must again prove progress (or pay the €1,000 per MW fee, at most twice) and, if land control rested on a promise, show it still holds it.
- Grid-back schedule : A schedule built backwards from the grid date: land option duration, permit filings, equipment orders, consultation, financing, ramp-up.
- Grid date : The date when the grid can actually deliver the project's target capacity, step by step.