A developer is interested in your land, or you think it could suit a data center. Before signing a promise or a lease, we help you understand what your land is worth for this kind of project, and what the contract should provide for.
You receive:
- a reading of the land's grid potential: nearby substations, network, plausible capacity
- planning and environmental constraints to anticipate
- points to discuss in the promise or lease, with your notary or lawyer
- the questions to put to the buyer
First conversation confidential and with no commitment. Fixed fees proposed in writing before any assignment. Best-efforts obligation.
A data center developer is interested in your land, or you think it could be. The question is not only the price offered: it is what the land is really worth for this use, what can increase that value, and when to commit.
THREE PATHS
Prepare before selling: grid connection request, planning, local dialogue, to sell land with documented value
Partner with a developer: land contribution, long lease or value sharing, with well-framed commitments
WHAT CREATES VALUE
Power (a solid connection request is not the same as being near a line), planning, local acceptance and a credible energisation date. See grid connection and planning and permits.
OUR RULES
When reviewing offers, we also check what is planned if the project stops (equipment removal, site restoration, guarantees), for your lawyer to address. See decommissioning safeguards.
We do not carry out property valuations; we work with a valuer or notary if needed. No commission on the sale, and never working for the buyer on the same land. Best-efforts obligation: grid and planning decisions are not ours.
What makes a connection request valuable: its queue position.
RAW LAND, POWERED LAND, POWERED SHELL: THREE DIFFERENT VALUES
Powered land: land whose capacity is committed with RTE or Enedis. An accepted PTF gives a queue position; a signed connection agreement commits a timeline. That document, more than the acreage, drives value
Powered shell: a connected building delivered weathertight, which the operator fits out. Value includes the building and the connection
For a landowner, the useful question is not "is a data center interested in my land?" but "which connection document exists, in whose name, and what happens to it if the project stops?". See our assignment examples.
Been offered an option by a developer? See selling or leasing land to a data center: what to know before signing.
HOW IT WORKS
WHAT WE COMMIT TO
Review of connection documents and the announced energisation date for a European data center developer, ahead of its investment decision. Audit of high-voltage equipment sourcing for a petrochemical group.
We do not design, build or sell equipment. No commission, no brokerage. Never on both sides of the same project.
Confidentiality agreement before any document. Professional liability insurance. Best-efforts obligation: only RTE and Enedis commit to capacity and a date.
FREQUENTLY ASKED QUESTIONS
What is powered land?
Land where access to significant power is documented and secured with the grid operator, so a data center can be hosted within a known timeline.
Should I sell my land to a data center developer right away?
Not necessarily. Value is created later through grid connection, planning and local dialogue. Preparing the land can change the negotiation, if cost and timing are measured.