Typical situation no. 5
A developer has identified 12 ha on the edge of a business park, 6 km from a 225 kV substation. The land is zoned for future development (AU) in the local land-use plan (PLU). The mayor is supportive, but the PLU amendment has not been launched.
WHAT IS BLOCKING
- An AU zone cannot be built on as it stands: a PLU amendment or revision is required, sometimes with an environmental assessment.
- Planning lead times can exceed those of the grid connection and become the real critical path.
- The project will probably require an environmental permitting procedure (generators, fuel oil storage, refrigerants).
WHAT WE DO
- Analysis of the zone regulations, development guidelines and easements.
- Inventory of the required procedures: planning, environment, possible public consultation.
- Construction of an integrated schedule for planning, permits and grid connection.
- Identification of the points to secure with the municipality and the inter-municipal authority.
WHAT YOU GET
- A realistic permitting schedule, with the critical path.
- The list of studies to launch and their sequence.
- An opinion on the feasibility of a 60 MW project on this site.
Typical format: Feasibility pre-study, about three weeks. Every assignment is scoped in writing before it starts.
THE EXPERT FOR THIS


Typical situation, based on real enquiries and anonymised. Figures are illustrative.
RELATED SITUATIONS
Our RTE connection offer states energisation in 2032. Is that credible?We have an RTE exploratory study for 120 MW but no connection offer (PTF). Can we sign the promise of sale for the land?The primary substation 4 km away shows capacity, but Enedis mentions reinforcement. Is 12 MW at MV (HTA) realistic?We want to start at 10 MW and scale to 40 MW. Should we request the full 40 MW now?See all 50 situations →