Typical situation no. 5
A developer has identified 12 ha on the edge of a business park, 6 km from a 225 kV substation. The land is zoned for future development (AU) in the local land-use plan (PLU). The mayor is supportive, but the PLU amendment has not been launched.
WHAT IS BLOCKING
- An AU zone cannot be built on as it stands: a PLU amendment or revision is required, sometimes with an environmental assessment.
- Planning lead times can exceed those of the grid connection and become the real critical path.
- The project will probably require an environmental permitting procedure (generators, fuel oil storage, refrigerants).
WHAT WE DO
- Analysis of the zone regulations, development guidelines and easements.
- Inventory of the required procedures: planning, environment, possible public consultation.
- Construction of an integrated schedule for planning, permits and grid connection.
- Identification of the points to secure with the municipality and the inter-municipal authority.
WHAT YOU GET
- A realistic permitting schedule, with the critical path.
- The list of studies to launch and their sequence.
- An opinion on the feasibility of a 60 MW project on this site.
Typical format: Feasibility pre-study, about three weeks. Every assignment is scoped in writing before it starts.
THE EXPERT FOR THIS


Typical situation, based on real enquiries and anonymised. Figures are illustrative.
RELATED SITUATIONS
We are taking over a brownfield site with a former 63 kV substation. Can it be reused for a data center?A small 2 MW regional AI data center: what building to look for, and what power to check before visiting?We want to convert an 8,000 m² logistics warehouse into a data center. Slab, clear height, power: will it work?We are coming from the United States and targeting France. Which region for 50 MW deliverable before 2029?See all 93 situations →