DefinitionArticle L. 342-24 of the French Energy Code allows RTE to reduce the capacity of a site that durably draws less than contracted. For agreements signed since 1 August 2025, two options: full capacity from the start, or a stepped ramp-up over up to ten years.

CAN RTE REDUCE A DATA CENTER'S CAPACITY?

A site that reserves a lot and uses little can see its capacity reduced. For an operator, the choice between full capacity and a stepped ramp-up is made when signing the agreement, based on its real leasing pace.