DefinitionArticle L. 342-24 of the French Energy Code allows RTE to reduce the capacity of a site that durably draws less than contracted. For agreements signed since 1 August 2025, two options: full capacity from the start, or a stepped ramp-up over up to ten years.
CAN RTE REDUCE A DATA CENTER'S CAPACITY?
A site that reserves a lot and uses little can see its capacity reduced. For an operator, the choice between full capacity and a stepped ramp-up is made when signing the agreement, based on its real leasing pace.
RELATED TERMS
- Annual adjustment of connection capacity : Since 1 August 2025, at both RTE and Enedis, the connection capacity of a site connected for at least five years is reset each year to 125% of the maximum it actually drew over the previous five years, without exceeding its current capacity.
- Connection agreement (convention de raccordement) : The contract that follows the PTF: scope, cost, schedule and, where relevant, capacity steps.
- Reserved versus firm capacity : A queue position reserves capacity, but the power actually available depends on grid works and reinforcements, sometimes in tranches, with possible operating limitations in between.
SAME TOPIC
Operating agreement · CART · TURPE · PTF transfer
← The full grid connection glossary · Our sources
A PROJECT AFFECTED?
Our independent experts apply these notions to your file, with no commission and no brokerage. The expert: Xavier Watrelos.