DefinitionSince 29 June 2024, a PTF can only be transferred to a company in the same group as the applicant, through an amendment signed with RTE. Buying a project with its connection in practice means buying the company that holds the PTF.

CAN A PTF BE TRANSFERRED?

This rule changes how projects are bought: you do not buy land "with its connection", you buy the company holding the PTF. Due diligence must therefore check the holder's legal structure and the PTF's history.