DefinitionTariff set by the French regulator CRE, paid by users for the use of transmission and distribution networks. For a data center it depends notably on subscribed power and load profile.
HOW DOES TURPE APPLY TO A DATA CENTER?
For a data center, TURPE is a lasting cost line that depends on subscribed power and load profile. It comes on top of the energy price and taxes: a business plan that leaves it out underestimates operating costs.
RELATED TERMS
- CART (transmission network access contract) : Contract governing the operating site's use of the transmission network: metering, subscribed power, access charges.
- Annual adjustment of connection capacity : Since 1 August 2025, at both RTE and Enedis, the connection capacity of a site connected for at least five years is reset each year to 125% of the maximum it actually drew over the previous five years, without exceeding its current capacity.
- PUE (Power Usage Effectiveness) : Ratio of the site's total energy to the energy used by IT equipment.
SAME TOPIC
Operating agreement · PTF transfer · Use it or lose it
← The full grid connection glossary · Our sources
A PROJECT AFFECTED?
Our independent experts apply these notions to your file, with no commission and no brokerage. The expert: Xavier Watrelos.