DefinitionSince 1 August 2025, at both RTE and Enedis, the connection capacity of a site connected for at least five years is reset each year to 125% of the maximum it actually drew over the previous five years, without exceeding its current capacity. Not to be confused with the rule allowing RTE to cap a request at 125% of justified capacity. The starting point: sites on the transmission grid subscribe only 48% of their connection capacity (14 GW out of 29 GW). Source: CRE decision 2024-229 (in French).
WHAT IS THE ANNUAL ADJUSTMENT OF CONNECTION CAPACITY?
For an existing site, capacity left unused for five years can be taken back. It is a key point when buying a data center: the connected capacity on paper is not necessarily what the site will have tomorrow.
RELATED TERMS
- Use it or lose it : Article L.
- Reserved versus firm capacity : A queue position reserves capacity, but the power actually available depends on grid works and reinforcements, sometimes in tranches, with possible operating limitations in between.
- Technical due diligence : Independent check, before an investment or a loan, of what drives a project's delivery: grid connection, equipment, permits, timeline.
SAME TOPIC
Operating agreement · CART · TURPE · PTF transfer
← The full grid connection glossary · Our sources
A PROJECT AFFECTED?
Our independent experts apply these notions to your file, with no commission and no brokerage. The expert: Xavier Watrelos.