DefinitionAbove roughly 40 MW, a project is generally connected by RTE at HTB rather than by Enedis at HTA. Below it, it may still need RTE if the primary substation is saturated.

WHY DOES THE 40 MW THRESHOLD MATTER FOR A DATA CENTER?

This threshold changes the counterpart, the procedure and often the schedule. A project hesitating between 35 and 50 MW must decide early: staying below can speed up connection, going above can add years.