DefinitionAbove roughly 40 MW, a project is generally connected by RTE at HTB rather than by Enedis at HTA. Below it, it may still need RTE if the primary substation is saturated.
WHY DOES THE 40 MW THRESHOLD MATTER FOR A DATA CENTER?
This threshold changes the counterpart, the procedure and often the schedule. A project hesitating between 35 and 50 MW must decide early: staying below can speed up connection, going above can add years.
RELATED TERMS
- HTA and HTB : Voltage levels.
- Primary substation (poste source) : Substation linking the transmission network (HTB) to the distribution network (HTA).
- Connection offer from Enedis (proposition de raccordement) : For a consumer connected to the distribution grid, at medium voltage or at low voltage above 36 kVA, Enedis issues a connection offer setting out the technical solution, cost and timeline.
SAME TOPIC
Customer substation · Reinforcement · MVA · IT MW · Power factor