DefinitionVoltage levels. HTA (1 to 50 kV, usually 20 kV) is Enedis's distribution network; HTB (above 50 kV: 63, 90, 150, 225 and 400 kV) is RTE's transmission network.

WHAT IS THE DIFFERENCE BETWEEN HTA AND HTB?

The voltage level determines the counterpart (Enedis or RTE), the procedure, the cost and the timeline. A data center of a few megawatts is usually connected at HTA; above roughly 40 MW it generally moves to HTB, with a private customer substation.