DefinitionPower available to the servers once cooling, electrical losses and auxiliaries are deducted. It is what an operator leases to its customers, and it is always lower than the connected capacity.

HOW DO YOU GO FROM CONNECTED CAPACITY TO IT MW?

Divide the site's active power by its PUE: with a PUE of 1.3, about 77% of active power reaches the servers. Rents and data centre value are calculated on IT MW, which is why they must not be confused with announced MVA.

CalculateOur MVA, MW and IT MW converter runs the numbers for your site: connected capacity, power factor, PUE.

RELATED TERMS

SAME TOPIC

HTA and HTB · Primary substation · Customer substation · The 40 MW threshold · Reinforcement

← The full grid connection glossary · Our sources

A PROJECT AFFECTED?

Our independent experts apply these notions to your file, with no commission and no brokerage. The expert: Xavier Watrelos.

Convert MVA, MW and IT MW →