DefinitionUnit of apparent power. Grid connections and transformers are sized in MVA: it includes reactive power, which flows on the network without doing useful work.
WHAT IS AN MVA, AND HOW DOES IT CONVERT TO MW?
To go from MVA to MW, multiply by the power factor (cos φ), often between 0.9 and 0.98 for a modern data centre. A 100 MVA connection therefore does not give 100 usable MW, let alone 100 IT MW.
CalculateOur MVA, MW and IT MW converter runs the numbers for your site: connected capacity, power factor, PUE.
RELATED TERMS
- Power factor (cos φ) : Ratio of active power (MW) to apparent power (MVA).
- IT MW (IT load) : Power available to the servers once cooling, electrical losses and auxiliaries are deducted.
- Customer substation (poste de livraison) : The site's own substation at the connection point, paid for by the developer.
SAME TOPIC
HTA and HTB · Primary substation · The 40 MW threshold · Reinforcement
← The full grid connection glossary · Our sources
A PROJECT AFFECTED?
Our independent experts apply these notions to your file, with no commission and no brokerage. The expert: Xavier Watrelos.