DefinitionSubstation linking the transmission network (HTB) to the distribution network (HTA). Its available capacity governs HTA connections.
WHAT IS A PRIMARY SUBSTATION?
Available capacity at the nearest primary substation is often the first filter for an HTA site. A saturated substation can require long works, or push the project to RTE even below 40 MW.
RELATED TERMS
- HTA and HTB : Voltage levels.
- The 40 MW threshold : Above roughly 40 MW, a project is generally connected by RTE at HTB rather than by Enedis at HTA.
- Reinforcement : Grid operator works (new transformer, line, substation) needed to accommodate the requested power, sometimes far from the site.