“100 MVA connected”, “70 IT MW”, “a 1 GW site”: these figures do not measure the same thing. This converter links the capacity connected to the grid to the power actually available to servers, the one that is leased and valued.

–MVA
–Active MW (site)
–Leasable IT MW
–of MVA not available to servers
–GWh used per year (site)

Order of magnitude: the result does not replace electrical design, nor a reading of the PTF or connection agreement.

THE THREE POWER FIGURES

MVA : apparent power, used for the connection and transformers.
MW : the site’s active power, equal to MVA multiplied by the power factor.
MW IT : the power available to servers, equal to MW divided by the PUE.

The formulaMW IT = MVA × cos φ ÷ PUE
Annual energy (MWh) = IT MW × PUE × 8,760 h × load factor

IT MW FOR 100 MVA CONNECTED

PUEcos φ 0.90cos φ 0.95cos φ 0.98
1.2757982
1.3697375
1.4646870
1.5606365

Calculation: 100 × cos φ ÷ PUE, rounded. A PUE of 1.2 is typical of a recent, efficient site; 1.5 of an older one.

WHAT THE CALCULATION DOES NOT TELL YOU

The converter starts from a connected capacity. It does not tell you when it will be available, or in which steps: that is the difference between reserved and firm capacity which depends on grid reinforcements and the grid date.

FREQUENTLY ASKED QUESTIONS

How many IT MW from 100 MVA of connection?

With a power factor of 0.95 and a PUE of 1.3, about 73 IT MW. Depending on PUE and power factor, the result ranges from roughly 60 to 82 IT MW.

What connection is needed for 10 IT MW?

With a PUE of 1.3 and a power factor of 0.95, about 13.7 MVA. The grid operator's capacity steps and design margins then need to be taken into account.

Why are announced MW not leasable MW?

Because part of the connected capacity goes to cooling, losses and reactive power. A site announced at 100 MW of connection offers clearly fewer IT MW to lease.