DefinitionRTE procedure for very large loads connected to the 400 kV network on sites identified by the State, targeting connection in three to four years. It requires a bank guarantee of 10% of extension works, then a down payment of 30% of total cost.

WHAT IS RTE'S HTB3 FAST-TRACK PROCEDURE?

It covers a small number of sites and very large projects. Its financial guarantees are high from the outset: it suits developers able to tie up large sums well before energisation.