A data center often has two battery systems: the UPS, which protects the servers, and increasingly a battery energy storage system (BESS), which manages the site's energy. Both contain batteries, but they sit in different places in the electrical design and do different jobs. Confusing them leads to poor sizing, and sometimes to surprises at the grid connection stage.

DOES YOUR SITUATION LOOK LIKE ONE OF THESE?

Anis MokdedAnis Mokded
Design, commissioning & operations
All situations →

1. WHERE THEY CONNECT

UPS = IN SERIES BESS = IN PARALLEL Grid UPSAC > DC > AC IT load Battery The load gets a rebuilt wave, with no break GridIT load BESSConverter + batteries ↕ both ways The load sees the grid as it is

The UPS is in series between the grid and the critical loads. It rectifies the current, charges its batteries, then rebuilds a clean wave. When the grid fails, the batteries take over with no interruption, while the generators start.

The BESS is in parallel. It connects to the site network through its own converter and exchanges energy both ways. The loads still see the grid as it is.

2. HOW THEY DIFFER

BESSUPS
Main jobManage energy for the whole siteProtect critical loads, with no break
AutonomyHoursMinutes
ResponseFast, with a transfer timeInstantaneous, no break
UsesPeak shaving, load shifting, renewables, grid servicesRide through until the generators start
CyclesDailyRare, on events
Power flowBoth waysUsually one way
PositionIn parallel with the loadsIn series with critical loads
Effect on the grid connectionAdds export and import capacityNone in itself, apart from losses and recharging

3. WHY A BESS IS NOT A BACKUP

A BESS designed for peak shaving or grid services cycles every day: when an outage hits, it may be nearly empty. It may also be committed to the grid and unavailable to the site. And unless it is designed for it, it cannot supply the loads without a break or hold an electrical island on its own. Data center availability requirements therefore always rely on UPS systems and generators.

The two can be combined if this is planned from the design stage: a BESS able to run in island mode, with a dedicated energy reserve, can reduce generator running time. Some "grid-interactive" UPS systems can also provide grid services. See grid-forming batteries and RTE's trial.

4. WHAT IT MEANS FOR THE GRID CONNECTION

A UPS does not change the connection request, except through its losses and battery recharging, which belong in the total power. A BESS adds export and import capacity. It changes the connection solution, the access conditions and sometimes the queue position. It is a decision to make before filing the request, not after. See the grid connection of a hybrid solar, battery and data center site.

Indicative orders of magnitude; each architecture is sized for the target availability, the generators and the grid connection contract.

FREQUENTLY ASKED QUESTIONS

What is the difference between a UPS and a BESS?

The UPS sits in series with critical loads and protects them with no break for a few minutes. The BESS sits in parallel and manages the site's energy for hours: peak shaving, load shifting, grid services.

Can a BESS replace a data center's UPS?

No. It does not provide uninterruptible power, it may be discharged or committed to the grid when an outage occurs, and it is not designed for that role without a specific architecture.

Can a BESS replace the generators?

Only partly, and only if designed to run in island mode with a dedicated reserve. It can reduce their running time, rarely remove them for a high-availability site.

Does a BESS change the grid connection request?

Yes. It adds export and import capacity, which changes the connection solution, the access conditions and sometimes the queue position.