HV grid connection & industrial projects
All situations →

Your data center project must connect to RTE's grid and you need to file your connection request. We prepare a complete, consistent file with you, then follow it through to the technical and financial proposal (PTF).

You receive:

  • the capacity and phasing to request, cooling and losses included
  • the request file and supporting documents, including the single-line diagram
  • follow-up of exchanges with RTE through to the PTF
  • a review of the PTF received, with the points to discuss

First conversation confidential and with no commitment. Fixed fees proposed in writing before any assignment. Best-efforts obligation.

Download or fill in: the PTF request checklist (PDF, 23 points).

The connection request is where most of the grid risk on a French data center is decided. What you ask RTE for, the power, the phases, the timeline, the connection point you have in mind, largely sets what you will get back in the technical and financial proposal (PTF). A poorly sized request is hard to fix: a significant change to the project means a new PTF and a new place in the queue.

THE PROBLEM

Developers and investors often arrive with an old exploratory study, a need expressed in MW of IT load and a target date. What is missing is the translation into a request RTE can process:

WHAT WE DO

Size the request

IT and total power, ramp-up, phases, fallback scenarios. We check that the request stays consistent with the project as it will be permitted.

Prepare the application

Technical data, site plan, timeline, land control needed at acceptance, the company that will hold the PTF. The application is reviewed before it is filed.

Deal with RTE

Preparing and following the exchanges with RTE's connection teams: technical questions, alternatives, phasing options. For very large loads, assessing RTE's fast-track procedure on identified sites.

Read the PTF and decide

Technical solution, works, cost, schedule, acceptance conditions and deadlines. We tell you what the announced date is worth and what could make it slip, before you commit.

YOUR EXPERT

Xavier Watrelos

Xavier Watrelos

HV grid connection & industrial projects

Engineer with 20+ years of industrial projects, including HV and MV grid connections, commissioning and operating permits. Read his profile →

WHO IT IS FOR

Data center developers and operators, investors and funds backing a project in France, advisers working for a foreign client. For projects from a few tens to several hundred MW. Below 40 MW, the request often goes to Enedis instead: we handle that case too.

WHAT YOU GET

Deliverables A sizing note: power, phases, assumptions
A complete application, reviewed before filing
Follow-up of the exchanges with RTE, with a written summary at each step
An analysis of the PTF received, with a clear recommendation before acceptance

WHAT TO HAVE READY

The target power and date, the site address or plots, the status of land control, any studies already done (exploratory study, internal studies) and the permit timeline. An exploratory study more than two years old is still a useful starting point, but says nothing about today's queue.

To understand the difference between an exploratory study, a PTF and a connection agreement, read which document actually secures a French site. For how an engagement runs (framing call, confidentiality, fixed-fee proposal), see how we work.

Sources: RTE procedures for connection requests from consumption installations on the transmission grid (Documentation Technique de Référence); CRE deliberations 2024-96, 2024-229 and 2026-32. The procedure changes regularly; the version that applies is the one in force when the request is filed. This page is general information, not legal advice.

For very large projects, see also PINM status (project of major national interest) and, for a site combining solar and storage, the grid connection of a hybrid project.

New in the Paris region: RTE is introducing capacity overbooking that frees at least 1 GW, with full power for data centers in exchange for a financial commitment and a gradual ramp-up. What it changes.

See also our grid connection engineering consultant page.

Once the offer is accepted, the place must be kept: keeping your queue position.

What RTE expects from a data center's electrical behaviour: grid readiness.

WHAT COULD CHANGE

RTE proposal, autumn 2026, subject to CRE approval PTF request fee: €42,000 excl. VAT today, raised to €100,000 excl. VAT in the proposal (still deducted from the first deposit if the offer is accepted)
First deposit on studies: from 30% to 50%
Land control and planning compliance (or procedures started) to be evidenced at the request stage
Two maturity checkpoints instead of the annual review; the schedule could be postponed twice, by six months at most
Removal from the queue if the project changes in nature, the connection point moves or capacity rises by more than 5% after the first checkpoint

These rules are not yet in force: they were consulted on from 24 September to 15 October 2026 and must be approved by the CRE. They follow the January to March 2026 consultation on "first ready, first served". The message is clear: filing will cost more, and a poorly prepared file will become riskier. See queue position.

Sources: Atlante, 26 October 2026; current €42,000 fee: RTE PTF general conditions and CRE decision 2026-32 of 4 February 2026 (in French).

HOW IT WORKS

A first conversation. You describe the project and the decision at stake. We tell you whether we can help, and who will be involved.
A confidentiality agreement. Signed before you send us any document.
A written, fixed-fee proposal. Scope, deliverables, timeline and fees set in advance: no open-ended time-based billing.
The assignment and debrief. A written deliverable, a debrief session, and the questions to put to the grid operator or your partners.

WHAT WE COMMIT TO

Recent assignments

Review of connection documents and the announced energisation date for a European data center developer, ahead of its investment decision. Audit of high-voltage equipment sourcing for a petrochemical group.

Independence

We do not design, build or sell equipment. No commission, no brokerage. Never on both sides of the same project.

Framework

Confidentiality agreement before any document. Professional liability insurance. Best-efforts obligation: only RTE and Enedis commit to capacity and a date.

DESCRIBE YOUR SITUATION

A few lines are enough: the project, the document or decision at stake, and your deadline. We come back to you to set up a first conversation.

First conversation confidential and with no commitment. Fixed fees proposed in writing before any assignment. Best-efforts obligation.

FREQUENTLY ASKED QUESTIONS

Who files the connection request with RTE?

The request is made in the name of the project company, which will sign and pay. We prepare the application with it and follow the exchanges with RTE at its side.

When does a project enter RTE's queue?

When the PTF is accepted, with the specific conditions signed without reservation, proof of land control, the first instalment and evidence of project progress, or instead a flat fee of €1,000 per MW.

Should we request the full power from the start?

Not necessarily. Phasing can be more realistic, but a significant power increase later may require a new PTF. It is a trade-off to settle before filing.

Is an old exploratory study enough?

No. It never reserved capacity and does not reflect today's queue. It is a starting point for preparing the request.