Typical situation no. 9
The permanent connection of a 20 MW site is scheduled in four years. To host a first customer from 2027, the developer is considering a temporary, rented 8 MW gas-fired plant until the grid arrives.
WHAT IS BLOCKING
- The cost per MWh generated on site is several times that of grid power, and weighs on margins throughout the period.
- A plant of this size falls under the regulations for classified installations: declaration, registration or authorisation depending on capacity.
- Noise, emissions and gas or fuel oil supply can undermine local acceptability.
WHAT WE DO
- Comparative economic model: temporary plant, waiting for the grid, or a different project phasing.
- Inventory of the required permits and their lead times.
- Analysis of operating constraints: redundancy, maintenance, fuel, switchover to the grid.
- Recommendations for negotiating the rental contract.
WHAT YOU GET
- A costed opinion on the merits of the solution.
- The list of permits and the associated schedule.
- The contractual points to watch.
Typical format: Opportunity study, two to three weeks. Every assignment is scoped in writing before it starts.
THE EXPERT FOR THIS


Typical situation, based on real enquiries and anonymised. Figures are illustrative.
RELATED SITUATIONS
Our RTE connection offer states energisation in 2032. Is that credible?We have an RTE exploratory study for 120 MW but no connection offer (PTF). Can we sign the promise of sale for the land?The primary substation 4 km away shows capacity, but Enedis mentions reinforcement. Is 12 MW at MV (HTA) realistic?We want to start at 10 MW and scale to 40 MW. Should we request the full 40 MW now?See all 50 situations →