Typical situation no. 34
A lender is monitoring a 40 MW project it has financed. The sponsor's quarterly report confirms commissioning at the end of 2027. Reading the appendices, the analyst finds that the main transformers have not yet been ordered.
WHAT IS BLOCKING
- With manufacturing lead times of two to three years, a 2027 date becomes highly unlikely.
- The sponsor does not flag the risk in its report.
- The lender must decide whether to exercise its contractual rights or accept the delay.
WHAT WE DO
- Review of the sponsor's schedule and the actual status of equipment orders.
- Estimate of a realistic commissioning date.
- Identification of levers to reduce the delay.
- Preparation of the questions to put to the sponsor.
WHAT YOU GET
- An alert note for the monitoring committee.
- A realistic commissioning date and its assumptions.
- Recommendations on how to proceed with the sponsor.
Typical format: Monitoring review, one to two weeks. Every assignment is scoped in writing before it starts.
THE EXPERT FOR THIS


Typical situation, based on real enquiries and anonymised. Figures are illustrative.
RELATED SITUATIONS
We are financing 60 MW. The sponsor says it has a signed connection offer (PTF). What is it really worth?Our fund owns three 2 to 6 MW data centers built between 2010 and 2016. Will they still be lettable in ten years?Our fund is classified Article 9. Which data center metrics can we actually document?Ahead of an acquisition, we have four weeks to complete the technical review of an operating 12 MW site.See all 50 situations →