Typical situation no. 4
A young company plans an AI inference data center in three phases: 10 MW in 2027, 25 MW in 2029, 40 MW in 2031. Its funding covers only the first phase. It is weighing a 10 MW connection request, which is faster, against a 40 MW request, which is more expensive and takes longer.
WHAT IS BLOCKING
- Requesting 10 MW today may mean filing a full new request, with a new lead time, to reach 40 MW.
- Requesting 40 MW now commits deposits and works sized for capacity that is not yet funded.
- The choice determines the connection voltage, the substation to be built and the site's electrical architecture.
WHAT WE DO
- Analysis of the applicable connection rules and of the options for a gradual capacity increase.
- Simulation of two or three strategies: cost, schedule, risks, financial commitment at each stage.
- Sizing of the substation and electrical architecture so as not to block later phases.
WHAT YOU GET
- A phased connection strategy, costed and dated.
- The points to negotiate with the grid operator.
- A memo usable in the fundraising pack.
Typical format: Advisory engagement, about two weeks. Every assignment is scoped in writing before it starts.
THE EXPERT FOR THIS

Typical situation, based on real enquiries and anonymised. Figures are illustrative.