Typical situation no. 2

A project sponsor has secured an option on 18 ha in Hauts-de-France. The seller is pressing to sign a promise of sale with a 10 % immobilisation fee. The only grid document available is an RTE exploratory study indicating capacity that is "conceivable" by 2030.

WHAT IS BLOCKING

WHAT WE DO

  1. Analysis of the exploratory study: assumptions, works mentioned, RTE's caveats.
  2. Assessment of competition on the target substation, based on known projects and public data.
  3. Drafting of the grid conditions precedent to include in the promise: obtaining a PTF, minimum capacity, latest date.
  4. Timing of the connection request aligned with that of the promise.

WHAT YOU GET

Typical format: Short review, one to two weeks. Every assignment is scoped in writing before it starts.

THE EXPERT FOR THIS

Xavier Watrelos

Xavier Watrelos

HV grid connection & industrial projects

View profile →

Typical situation, based on real enquiries and anonymised. Figures are illustrative.