Typical situation no. 2
A project sponsor has secured an option on 18 ha in Hauts-de-France. The seller is pressing to sign a promise of sale with a 10 % immobilisation fee. The only grid document available is an RTE exploratory study indicating capacity that is "conceivable" by 2030.
WHAT IS BLOCKING
- An exploratory study does not bind RTE: it reserves no capacity and may be contradicted by the connection offer (PTF).
- In the meantime, other requests may be filed on the same substation.
- The sponsor risks tying up several hundred thousand euros on land whose power is not guaranteed.
WHAT WE DO
- Analysis of the exploratory study: assumptions, works mentioned, RTE's caveats.
- Assessment of competition on the target substation, based on known projects and public data.
- Drafting of the grid conditions precedent to include in the promise: obtaining a PTF, minimum capacity, latest date.
- Timing of the connection request aligned with that of the promise.
WHAT YOU GET
- A clear opinion: sign, sign with conditions, or wait.
- Model wording for the grid clauses, to pass on to the notary.
- A backward schedule for the PTF request and the promise of sale.
Typical format: Short review, one to two weeks. Every assignment is scoped in writing before it starts.
THE EXPERT FOR THIS

Typical situation, based on real enquiries and anonymised. Figures are illustrative.
RELATED SITUATIONS
Our RTE connection offer states energisation in 2032. Is that credible?The primary substation 4 km away shows capacity, but Enedis mentions reinforcement. Is 12 MW at MV (HTA) realistic?We want to start at 10 MW and scale to 40 MW. Should we request the full 40 MW now?Our 12 ha plot is in an AU zone of the local land-use plan (PLU). Can we build a 60 MW data center on it?See all 50 situations →