Typical situation no. 3

A regional operator wants to build a 12 MW data center near Lyon. Public maps show available capacity at the nearest primary substation. Yet the Enedis pre-study mentions reinforcement and a 30-month lead time.

WHAT IS BLOCKING

WHAT WE DO

  1. Review of the Enedis pre-study and identification of what triggers the reinforcement.
  2. Comparison of three options: MV (HTA) on a dedicated feeder, MV (HTA) in two tranches, HV (HTB) with a customer substation.
  3. Cost and lead-time estimates for each option, with their risks.
  4. Preparation of the technical discussion with Enedis.

WHAT YOU GET

Typical format: Desk review and discussion with Enedis, about two weeks. Every assignment is scoped in writing before it starts.