Typical situation no. 65
A European neocloud wants to set up in the Paris region and is negotiating 5 MW in a data center under extension. The operator announces delivery in nine months, 80 kW racks and liquid cooling. The contract carries a five-year commitment.
WHAT IS BLOCKING
- The tenant does not know whether power is connected, requested or merely hoped for.
- Cooling 80 kW racks depends on equipment not yet installed.
- Contract delay penalties are small compared with the tenant's commitment.
WHAT WE DO
- Check of the connection document and the realistic energisation date.
- Review of power and cooling design for the target densities.
- Site visit and review of works progress and equipment orders.
- List of clauses to strengthen: delivery, penalties, expansion, SLAs.
WHAT YOU GET
- An independent view before a five-year commitment.
- Better-protected contract clauses.
- A realistic start date to plan GPU arrival.
Typical format: Pre-lease audit, two to three weeks. Every assignment is scoped in writing before it starts.
THE EXPERT FOR THIS


Typical situation, based on real enquiries and anonymised. Figures are illustrative.
RELATED SITUATIONS
Our RTE connection offer states energisation in 2032. Is that credible?We have an RTE exploratory study for 120 MW but no connection offer (PTF). Can we sign the promise of sale for the land?The primary substation 4 km away shows capacity, but Enedis mentions reinforcement. Is 12 MW at MV (HTA) realistic?We want to start at 10 MW and scale to 40 MW. Should we request the full 40 MW now?See all 68 situations →