The problem. An incomplete or poorly sized connection request is hard to fix: a significant change to the project often means a new request. This checklist sets out, in 23 points, what to gather and check before filing, then what to read in the PTF received.
Site and land: 3 points
The intended connection: 4 points
Technical requirements: 2 points
Schedule and permits: 3 points
Financial commitments: 3 points
Once the ptf is received: 4 points
GOING FURTHER
For a specific file, we prepare the request with you and follow it through to the PTF: see PTF request support. Already received a PTF? See grid connection offer review.
FREQUENTLY ASKED QUESTIONS
Does the checklist replace RTE's documents?
No. It helps prepare the file; the applicable requirements are those of RTE's or Enedis's technical reference documentation and procedures in force.