Typical situation no. 59
A producer operates a plant connected to RTE's grid. It is considering a data center on the same site, possibly with battery storage, and wonders whether it can rely on its existing connection.
WHAT IS BLOCKING
- An export connection does not automatically give import rights.
- Sharing capacity between generation, storage and consumption follows precise rules.
- The business case depends on network tariffs and power sales contracts.
WHAT WE DO
- Analysis of the existing connection and the steps required with RTE.
- Study of possible configurations: consumption only, with generation and storage.
- First sizing of storage and its role.
- Roadmap of steps and timeline.
WHAT YOU GET
- A clear answer on what can be reused.
- Possible connection configurations and their consequences.
- A realistic timeline.
Typical format: Feasibility study, three to five weeks. Every assignment is scoped in writing before it starts.
THE EXPERT FOR THIS


Typical situation, based on real enquiries and anonymised. Figures are illustrative.
RELATED SITUATIONS
Our RTE connection offer states energisation in 2032. Is that credible?We have an RTE exploratory study for 120 MW but no connection offer (PTF). Can we sign the promise of sale for the land?The primary substation 4 km away shows capacity, but Enedis mentions reinforcement. Is 12 MW at MV (HTA) realistic?We want to start at 10 MW and scale to 40 MW. Should we request the full 40 MW now?See all 93 situations →