Typical situation no. 8
A real estate group is buying a former 25 ha paper mill in eastern France. The site has a 63 kV delivery substation that supplied the plant until 2021, with 18 MW of contracted capacity. The buyer hopes to save several years on the grid connection.
WHAT IS BLOCKING
- It is not certain that the connection capacity is retained if the grid access contract has been terminated or if the site has remained inactive.
- The substation equipment is over thirty years old: its condition and compliance are unknown.
- A data center requires a level of redundancy the former substation probably did not provide.
WHAT WE DO
- Verification of the contractual position with the grid operator: contract, capacity, conditions for takeover.
- Technical inspection of the substation: transformers, switchgear, protection systems, civil works.
- Study of the options: reuse, refurbishment, or a new substation while retaining existing rights.
- Recommendations on the steps to take before signing the acquisition.
WHAT YOU GET
- A substation condition report with photos and recommendations.
- An estimate of the capacity actually available and the time needed to obtain it.
- The clauses to include in the acquisition deed.
Typical format: Desk review and site visit, about three weeks. Every assignment is scoped in writing before it starts.
THE EXPERT FOR THIS

Typical situation, based on real enquiries and anonymised. Figures are illustrative.
RELATED SITUATIONS
Our RTE connection offer states energisation in 2032. Is that credible?We have an RTE exploratory study for 120 MW but no connection offer (PTF). Can we sign the promise of sale for the land?The primary substation 4 km away shows capacity, but Enedis mentions reinforcement. Is 12 MW at MV (HTA) realistic?We want to start at 10 MW and scale to 40 MW. Should we request the full 40 MW now?See all 50 situations →