DefinitionOn-site generation (gas engines, batteries, generators) supplying all or part of a data centre until the grid connection arrives. It needs its own permits.
WHAT IS BRIDGING POWER FOR A DATA CENTRE?
It lets a site start before full connection, but it has a cost, emissions and its own permits, often under the ICPE regime. Its real duration depends on the grid date: a solution planned for two years can last longer.
RELATED TERMS
- ICPE : French environmental permitting regime.
- Hybrid supply : Combining several sources (grid, solar, batteries, on-site generation) to supply a site or smooth its demand.
- Grid date : The date when the grid can actually deliver the project's target capacity, step by step.