DefinitionUptime Institute classification, I to IV, describing a data centre's redundancy and availability. Certification is issued by the Uptime Institute.
WHAT DO DATA CENTRE TIER LEVELS MEAN?
The Tier level describes the site's design and redundancy, not its energisation date or available power. A site "designed to Tier III" is only certified if the Uptime Institute has actually certified it.
RELATED TERMS
- Bridging power : On-site generation (gas engines, batteries, generators) supplying all or part of a data centre until the grid connection arrives.
- Technical due diligence : Independent check, before an investment or a loan, of what drives a project's delivery: grid connection, equipment, permits, timeline.
- DORA : EU Regulation 2022/2554 on digital operational resilience, applicable since 17 January 2025: banks, insurers and asset managers must manage the risks of their ICT providers, including data centres.
SAME TOPIC
← The full grid connection glossary · Our sources
A PROJECT AFFECTED?
Our independent experts apply these notions to your file, with no commission and no brokerage. The expert: Francis Gillard.