A site can look ideal for a data center (large plot, business zone, motorway nearby) and fail on a single point: a saturated substation, a flood zone, an approach path, a listed landscape. These red flags can be checked in a few weeks. Finding them after signing a sale agreement costs months, and sometimes the project.

Here are the thirteen checks our engineers run first, before any detailed study.

THE 13 POINTS TO CHECK

In the order they most often sink a project 01. Grid connection : Distance to and capacity of the nearest substation, likely RTE or Enedis timeline, cost of works.
02. Flooding : Flood risk prevention plan, groundwater rise, flood history.
03. Industrial risk : Proximity to an upper-tier Seveso site and technological risk perimeters.
04. Aviation constraints : Approach paths, height limits, radars.
05. Zoning : Local plan zoning, whether the "warehouse" use is allowed, any change needed and its timeline.
06. Heritage and landscape : Listed sites, surroundings of historic monuments, visibility.
07. Natural areas : Natura 2000, protected areas, wetlands, protected species to survey.
08. Woodland : Possible clearing, authorisation and compensation.
09. Neighbours : Distance to homes, noise from generators and cooling, construction traffic.
10. Water : Availability and network capacity, cooling choice.
11. Soil : Possible contamination, geotechnical studies, foundations.
12. Access and fibre : Road access for construction and operations, nearby fibre networks.
13. Local acceptance : Elected officials' position, consultations and opposition locally or nearby.

GET THE LIST AS A PDF

One page, thirteen checks for your site. The download link appears as soon as you submit.

We may contact you about your site. Your data is never sold or shared.

HOW WE CHECK THEM

Public data first (hosting-capacity maps, risk plans, easements, zoning, ecological inventories), then a site visit and initial discussions with the grid operator and the municipality. The result: a clear note, point by point, on what is secured, what remains to study and what blocks. See also our capacity test-fit and our site readiness pack.

THE ENGINEERS INVOLVED

Xavier Watrelos, grid connection: 20+ years of industrial projects, including HV and MV connections.

Frédéric Arnaud, coordination and investment: overall reading of the file and its value for an investor.

Full profiles: our experts.

HOW WE WORK

A fixed-fee written proposal, paid by you alone. No commission on the sale or lease of the land: we do not look for buyers and have no stake in the transaction.

FREQUENTLY ASKED QUESTIONS

What is the first thing to check on a data center site?

Grid connection: without power available within a reasonable timeframe, no other strength of the site matters.

Is a site in an agricultural or natural zone ruled out?

Not necessarily, but the local plan must change, which takes time and exposes the project to public consultation. It must be assessed very early.

How long does it take to check these points?

An initial analysis from public data and a site visit usually takes two to three weeks.