A data center developer is offering a sale agreement (promesse de vente) on your land in France. The price looks attractive, but the sale will only happen if a long list of conditions is met, often over several years. Meanwhile, the land is tied up. Understanding these conditions, their duration and their consequences is the owner's best protection.
THE USUAL CONDITIONS PRECEDENT
Zoning: an operational planning certificate, or a change to the local plan
Soil: geotechnical and contamination studies with no incompatible constraint
Water: water law file, no incompatible wetland
Biodiversity: four-season fauna and flora survey, with no blocking protected species
Building permit: granted and free of any appeal or withdrawal
Environmental authorisation: classified-installation (ICPE) authorisation or registration, free of any appeal
Each is legitimate for the buyer. Together, they can delay the sale by two to four years and keep it uncertain to the end.
CLAUSES TO WATCH, FOR THE OWNER
Amount of the immobilisation fee and when it is yours to keep
Substitution right: who the final buyer will really be, and how solid financially
Interim milestones: dates by which the grid request, permit and authorisation must be filed
What happens to studies and the grid offer if the sale falls through
Works, surveys and site access allowed during the agreement
Without milestones, an agreement can tie up your land for years with no progress. A realistic grid and permitting timeline lets you negotiate credible dates.
WHAT WE DO FOR THE OWNER
We check, for you alone, that the proposed conditions and timelines are realistic: grid feasibility and likely RTE or Enedis timeline, planning path, environmental risks, robustness of the developer's project. We work alongside your notary and lawyer, who draft and negotiate the deed. See also the 13 red flags to check on a site.
HOW WE WORK
A fixed-fee written proposal, paid by you alone. We do not look for buyers, do not negotiate the sale and take no commission: our only interest is that your land is committed on the right terms.
FREQUENTLY ASKED QUESTIONS
How long does a data center land sale agreement last in France?
Often two to four years, to obtain the grid connection, building permit and environmental authorisation. Length and extensions are negotiable.
What is the immobilisation fee?
A sum the buyer pays or commits to pay in return for tying up the land; the conditions under which it is refunded are a key negotiating point.
Do you replace the notary or lawyer?
No. They draft and negotiate the deed. We provide the technical analysis of grid connection, permits and timelines.