The problem. A data centre operator must now meet three obligations at once: report energy indicators every year, deal with waste heat and meet the conditions for the reduced electricity excise rate. Each has its own threshold, date and authority. A single missing condition is enough to lose the reduced rate, and a failure to report can lead to a public formal notice.
THE CALENDAR
Sites of 500 kW IT and above (per legal establishment): previous-year data submitted and published on a dedicated web page. A new site reports within two months of commissioning.
The reduced electricity excise rate depends on cumulative conditions. Tighter requirements, notably on water and energy, are announced from 2027. The implementing text has yet to be published.
Energy rating for data centres of 500 kW IT and above, adopted by EU delegated regulation on 21 September 2026.
Sites of 1 MW and above whose permit was filed before 1 January 2026: analysis of heat recovery options due by this date if the ERF threshold of 0.20 is not met.
Server rooms must meet PUE thresholds set according to their floor area.
OUR ANSWER
A fixed-price diagnostic for sites of 500 kW to 10 MW: where the site stands on each obligation, what is missing, and in which order to address it. It is led by Geoffrey Garriga for energy and building controls, and Francis Gillard for operations.
See also: PUE, WUE and ERF reporting · ERF · A–G rating.
FREQUENTLY ASKED QUESTIONS
Is my data centre affected?
Annual reporting covers sites of 500 kW IT and above; the waste heat obligation, sites of 1 MW and above; the reduced excise rate, sites that claim it. A site can fall under all three.
What happens if a site does not report?
A formal notice, which may be made public, then an administrative fine of up to €50,000 per data centre.
Does the checklist replace legal advice?
No. It summarises public rules and refers to their sources. Some announced texts are not yet published.
Sources: decree no. 2025-1382 of 29 December 2025; French Ministry for Ecological Transition, energy efficiency of data centres; article L. 312-70 of the French tax code on goods and services; French Senate economic affairs committee report on bill no. 435 (February 2026); EU delegated regulation of 21 September 2026.