Typical situation no. 16
A project developer has land with available power 35 km from Toulouse. Its prospects are concerned about the distance: response times for inference applications, and the cost and lead time of the fibre.
WHAT IS BLOCKING
- The latency added by 35 km of fibre is low, but the actual route can be twice as long as the straight-line distance.
- Without available dark fibre, a link must be built or leased, sometimes over several years.
- Customers need figures, not reassurances.
WHAT WE DO
- Calculation of actual latency for the possible routes.
- Inventory of available fibre infrastructure and of carriers able to serve the site.
- Costing of a redundant link using dark fibre or leased capacity.
- Quantified case for prospects.
WHAT YOU GET
- A connectivity note with measured or calculated latencies.
- The link options with costs and lead times.
- A case to present to customers.
Typical format: Connectivity study, two to three weeks. Every assignment is scoped in writing before it starts.
THE EXPERT FOR THIS


Typical situation, based on real enquiries and anonymised. Figures are illustrative.
RELATED SITUATIONS
Our RTE connection offer states energisation in 2032. Is that credible?We have an RTE exploratory study for 120 MW but no connection offer (PTF). Can we sign the promise of sale for the land?The primary substation 4 km away shows capacity, but Enedis mentions reinforcement. Is 12 MW at MV (HTA) realistic?We want to start at 10 MW and scale to 40 MW. Should we request the full 40 MW now?See all 50 situations →