Typical situation no. 90
A developer has heard that the law now allows a data center to be designated a project of major national interest. Its land requires a change to the local plan and the schedule is tight. It wants to know whether this route is open and what it brings.
WHAT IS BLOCKING
- Designation is made by decree.
- It can ease alignment of planning documents, with the municipality's or intermunicipal authority's agreement.
- It does not exempt the project from water and biodiversity studies, nor from the grid connection.
WHAT WE DO
- Analysis of the project's eligibility under the law of 26 May 2026.
- Compared timeline: standard procedure and the major national interest route.
- Points to prepare: water, biodiversity, local acceptance, grid connection.
- Questions to put to State services and the local authority.
WHAT YOU GET
- A clear view of what the procedure does and does not bring.
- A realistic timeline.
- A better-prepared file for discussions with the State.
Typical format: Regulatory diagnostic, two to three weeks. Every assignment is scoped in writing before it starts.
THE EXPERTS FOR THIS


Typical situation, based on real enquiries and anonymised. Figures are illustrative.
RELATED SITUATIONS
Our 12 ha plot is in an AU zone of the local land-use plan (PLU). Can we build a 60 MW data center on it?An RTE "fast-track" site or a standalone site in Grand Est: which to choose for 300 MW?A developer wants 30 ha of our farmland for a data center. Does France's zero net land take policy allow it?