Typical situation no. 7

A developer has obtained its connection agreement for 90 MW. The customer substation requires two 225/20 kV, 80 MVA transformers. The first manufacturer consulted quotes a 140-week lead time, pushing commissioning past the date promised to the future tenant.

WHAT IS BLOCKING

WHAT WE DO

  1. Review of the specifications to identify what can be standardised without loss of performance.
  2. Wider consultation of European and non-European manufacturers, with checks on their references and actual production capacity.
  3. Study of alternatives: released production slots, refurbished equipment, substation phasing.
  4. Procurement plan integrated into the construction schedule.

WHAT YOU GET

Typical format: Procurement and engineering engagement, four to six weeks. Every assignment is scoped in writing before it starts.

THE EXPERT FOR THIS

Xavier Watrelos

Xavier Watrelos

HV grid connection & industrial projects

View profile →

Typical situation, based on real enquiries and anonymised. Figures are illustrative.

RELATED SITUATIONS