DefinitionA schedule built backwards from the grid date: land option duration, permit filings, equipment orders, consultation, financing, ramp-up.

HOW IS A GRID-BACK SCHEDULE BUILT?

You start from the grid date and work backwards: each step must be finished in time for the next. This brings out the critical tasks, often permits and transformer orders, that a conventional forward schedule hides.