DefinitionA schedule built backwards from the grid date: land option duration, permit filings, equipment orders, consultation, financing, ramp-up.
HOW IS A GRID-BACK SCHEDULE BUILT?
You start from the grid date and work backwards: each step must be finished in time for the next. This brings out the critical tasks, often permits and transformer orders, that a conventional forward schedule hides.
RELATED TERMS
- Grid date : The date when the grid can actually deliver the project's target capacity, step by step.
- Deadline register : A table tracking everything that can cost a project time or capacity: annual queue review, capacity steps, land option expiry, appeal periods, manufacturing slots.
- Time to Connect : Real time between a project decision and energisation.