Large data centers are often built on farmland. Behind the hectares there are farmers, sometimes a family that has worked the land for generations, who learn about the project at the same time as everyone else. "Nobody asked our opinion" is one of the hardest criticisms to answer in a public meeting. Farmers must be met first, and their situation handled seriously, well before the public consultation.
First conversation confidential and with no commitment. Fixed fees proposed in writing before any assignment.
LANDOWNER AND FARMER: TWO DIFFERENT PEOPLE
The sale agreement is signed with the landowner. But the land is often farmed by a tenant under a rural lease. The tenant has rights: they cannot be evicted without compensation, and losing a few dozen hectares can upset the balance of the whole farm. A project that has secured the land with the owner but not spoken to the farmer has solved only half the problem.
WHAT FRENCH LAW REQUIRES
Projects subject to a mandatory environmental impact assessment that take land farmed in recent years must assess their effect on the local farming economy (article L.112-1-3 of the rural code). The default threshold is 5 hectares; the prefect may set a local threshold between 1 and 10 hectares.
The study sets out measures to avoid, reduce and then compensate losses to local agriculture, funded by the developer and reviewed by the prefect after the departmental farmland commission (CDPENAF).
Separate from collective compensation: it covers the farmer's own loss. Scales and protocols vary by department and are often negotiated with the chamber of agriculture.
Amendments to this regime are under discussion in Parliament: conditions must be checked for each project at the time of filing.
OUR ASSIGNMENT
We do not negotiate on behalf of the parties and we are not estate agents: we prepare the file, organise the dialogue and check commitments are kept. See also our community engagement pack.
WHO IS INVOLVED
A network expert specialised in financial advisory and agricultural land, with, as needed:

Xavier Watrelos
HV grid connection & permitting
Over twenty years of industrial projects, HV connections, utilities, commissioning and permit applications. Read profile →
FREQUENTLY ASKED QUESTIONS
Does a data center on farmland need an agricultural impact study in France?
Yes if three conditions are met: the project requires a mandatory environmental impact assessment, it takes land farmed in recent years, and the area reaches the local threshold (5 hectares by default, 1 to 10 hectares depending on the department).
What is the difference between collective agricultural compensation and the farmer's compensation?
Collective compensation offsets the loss to the local farming economy and funds collective projects. The farmer's compensation covers the tenant's own loss. Both can apply.
When should farmers be approached on a data center project?
Before any public announcement. A farmer who learns about the project from the press almost always becomes an opponent.