Our clients ask for confidentiality, and we name no client without written consent. Rather than a wall of logos, here are eight typical assignments as we run them: the starting situation, the deliverables, the indicative duration and the expert involved.
These examples are composite and anonymised: they describe typical assignments, not a specific client or project. Durations are indicative and depend on the file and grid operator timelines. Our commitment is a best-efforts obligation.
1. PREPARING THE GRID CONNECTION REQUEST
Deliverables: Review of the exploratory study, PTF request file, single-line diagram in principle, follow-up of RTE's review and reading of the PTF before acceptance.
Indicative duration: Three to six months, depending on RTE
Who is involved: A high-voltage engineer, with GridReadiness coordinating
See: RTE connection request
2. CHECKING THE ANNOUNCED POWER BEFORE AN OFFER
Deliverables: Red flag memo on documents: type of connection document, queue entry date, deadlines, capacity actually justified, remaining works.
Indicative duration: Two to four weeks
Who is involved: A high-voltage engineer and GridReadiness
See: Power claim verification
3. LENDER'S TECHNICAL ADVISOR
Deliverables: Review report: grid connection, transformers, permits, schedule risks and points to cover in the finance documents.
Indicative duration: Three to six weeks
Who is involved: A high-voltage engineer and GridReadiness
See: Lender due diligence
4. ASSESSING A PLOT'S DATA CENTER POTENTIAL
Deliverables: Potential memo: nearest substation, published capacity, raw land vs land with a PTF vs land with a connection agreement, points to watch in the option.
Indicative duration: Three to six weeks
Who is involved: A high-voltage engineer and GridReadiness, with a lawyer if needed
See: Landowners
5. HOSTING A PROJECT WITH EYES OPEN
Deliverables: Questions and safeguards memo, review of the developer's documents, preparation of public meetings.
Indicative duration: Four to eight weeks
Who is involved: A community acceptance specialist and GridReadiness
See: Local authorities
6. DENSIFYING FOR AI
Deliverables: Capacity and operations audit, additional power need, approach to the grid operator, action plan.
Indicative duration: Four to eight weeks
Who is involved: A former head of critical-site operations and a high-voltage engineer
See: Operations audit
7. SECURING HIGH-VOLTAGE EQUIPMENT
Deliverables: Procurement strategy: specifications, makers to consult, order windows, schedule risks.
Indicative duration: Two to four weeks
Who is involved: A high-voltage engineer
See: Transformer lead times
8. REGAINING CONTROL OF A CONTESTED PROJECT
Deliverables: Diagnosis, response plan, preparation of public meetings and of discussions with elected officials and State services.
Indicative duration: Depending on the situation, from the first days
Who is involved: A crisis management and acceptance specialist
See: Crisis management
See also the firm, our experts and the situations we handle.
FREQUENTLY ASKED QUESTIONS
Why don't you name your clients?
Most data center projects remain confidential until a late stage. We name a client only with written consent. These examples describe what we do without identifying any project.
How much does an assignment cost?
Each assignment is covered by a written proposal with scope, deliverables, timeline and a price fixed in advance, after a first conversation.