Typical situation no. 66

An operator is financing equipment for a 20 MW AI site. Servers are ordered and deliverable in spring. The building is on track, but the connection substation is only promised for the following winter, and liquid cooling needs works nobody had priced. The lender worries about paying for machines that will sit idle for months.

WHAT IS BLOCKING

WHAT WE DO

  1. Check of the connection document and the realistic energisation date.
  2. Options to start earlier: smaller first phase, temporary power, phasing.
  3. Comparison of two purchase schedules: delivery as planned, or aligned with energisation.
  4. Review of delay clauses in customer, supplier and connection contracts.

WHAT YOU GET

Typical format: Targeted review, two to four weeks. Every assignment is scoped in writing before it starts.

THE EXPERT FOR THIS

Xavier Watrelos

Xavier Watrelos

HV grid connection & industrial projects

View profile →
Frédéric Arnaud

Frédéric Arnaud

Founder & coordinator

View profile →

Typical situation, based on real enquiries and anonymised. Figures are illustrative.