Every week, what moved for data center projects in France, and what it changes for a developer, investor, landowner or local authority. Sourced facts only.
1. GRID: RTE WANTS TO SERVE READY PROJECTS FIRST
On 9 November at the Ministry of the Economy, Anne Le Hénanff, minister for AI and digital affairs, defended the reform prepared by RTE: replacing "first come, first served" with "first ready, first served". According to DCMag (11 November), nearly 33 GW of requests from more than 200 projects (data centres, hydrogen, heavy industry) are waiting for a connection. RTE plans 9 GW of additional hosting capacity by 2029 in Dunkirk, Le Havre and Fos, 5 GW in five other zones (south of Île-de-France, south Alsace, Saint-Avold, Valenciennes-Maubeuge, Port-la-Nouvelle), and a fast track for five projects of 700 to 2,000 MW on sites identified by the State, for commissioning in 2028-2029. RTE has already tightened the evidence it asks for: land control, a forecast schedule, progress on permits (L'Energeek, 9 November). The reform is not yet in force. In its decision 2026-32 of 4 February 2026, the regulator CRE asked RTE to submit a first revision of the procedure, better reflecting project maturity, by 1 October 2026 at the latest. We have found no published approval so far.
What it changes: a queue position will be worth what the file is worth. Land control, permits under way, a credible schedule: these will set the rank, no longer the date of the request. See your position in the queue and preparing a PTF request.
2. PERMITS: THREE PROJECTS SUSPENDED OR ANNULLED
La Tribune (10 November) reports three recent decisions: the Alixan data centre project (Drôme) has been suspended, and Segro's project at Le Bourget (north of Paris) and BXIA's in Bordeaux have been annulled.
What it changes: a permit granted is not a final permit. Appeal periods, pending litigation and relations with the municipality are checked before any commitment. See planning and permits.
3. HAUTS-DE-FRANCE: THE REGIONAL COUNCIL REJECTS A MORATORIUM
On 12 November, the Hauts-de-France regional council heavily rejected a moratorium on data centres proposed by the Green group. According to France 3 (13 November), 19 projects are under way in the region.
What it changes: regional support holds, but acceptance is won municipality by municipality. See our opposition tracker.
4. TEXAS: THE FALL OF THE MATADOR PROJECT
Le Monde (10 November) describes the troubles of the Matador project in Amarillo, presented as one of the largest data centre complexes in the United States. The company behind it, Fermi, is reportedly worth about $1 billion on the stock market, twenty times less than at its listing a year earlier. No firmly committed customers, works halted then restarted with three gas plants, founders at odds.
What it changes: the three signals a due diligence would have flagged are in the article: no committed tenant, bridge power on gas for lack of a grid connection, fragile local acceptance. See lender due diligence.
5. COLOCATION RENTS: THE PRICE OF A MONTH'S DELAY
According to JLL, quoted by La Lettre M² (November), average colocation rents on the main European markets (Frankfurt, London, Amsterdam, Paris, Dublin) are €177 per kW per month for contracts around 500 kW, €147 for 1 to 5 MW and €123 above 5 MW.
What it changes: a month's delay pushes back roughly €123,000 to €177,000 of rent per leased MW. That is revenue, not margin, and averages across five markets, not Paris rents. See the delay cost calculator.
6. BÉTHUNE: WHAT NEBIUS'S RESULTS SAY
Nebius, tenant of the Béthune data centre operated by Azur Datacenter, published its third-quarter results on 12 November. No figure is given for Béthune: France is listed among its sites, with no breakdown by site. Management said part of its third-party colocation capacity, including New Jersey, is slipping into 2027, with power as the main constraint. France was not discussed.
What it changes: even for a leading tenant, power sets the date. See our Béthune case study.
7. TAX: A DECREE ON THE REDUCED ELECTRICITY EXCISE RATE
According to IT for Business, a decree tightening access to the reduced excise rate on electricity, worth a reduction of more than 60% in taxes, has been announced. Its criteria and timing are still to be set.
What it changes: a business plan that relies on this rate should be tested without it until the text is published.
AGENDA
22 November: end of the consultation on the Éguzon-Marmagne line
4 December: Citel webinar on lightning protection for data centres
Sources: DCMag, 11 November 2026; L'Energeek, 9 November 2026; IT for Business, November 2026; CRE decision no. 2026-32 of 4 February 2026; La Tribune, 10 November 2026; France 3 Hauts-de-France, 13 November 2026; Le Monde, 10 November 2026; JLL via La Lettre M², November 2026; Nebius press release and shareholder letter of 12 November 2026. Company positions are presented as such.
FREQUENTLY ASKED QUESTIONS
How often is this published?
Every week, on our blog and on the GridReadiness LinkedIn page.
NEXT STEP
Assessing a data center project in France? We establish what really sets its energisation date: grid connection, equipment, permits. The expert: Xavier Watrelos.
THE GRIDREADINESS MONTHLY LETTER
Grid connection, equipment and data center projects in France: what matters, once a month.
Your email is used only for this letter. Legal notice.
Thank you, you are subscribed.
Sending failed. Email fred@gridreadiness.com.