The problem. A data center project moves on several fronts at once, and the weakest one sets the date. These twelve questions place your project in two minutes and show which points to address first.
1. Land control
2. Grid connection document
3. Capacity confirmed in writing versus need
4. Power requirement quantified (cooling and phasing included)
5. Energisation date
6. Long-lead equipment (transformers, switchgear)
7. Planning and permits
8. Local context
9. Water and waste heat (ERF above 1 MW)
10. Customer or end user
11. Financing
12. Project steering
Points to address first
Indicative scorecard based on your answers. It does not replace a review of the project documents.
HOW IT WORKS
WHAT WE COMMIT TO
Review of connection documents and the announced energisation date for a European data center developer, ahead of its investment decision. Audit of high-voltage equipment sourcing for a petrochemical group.
We do not design, build or sell equipment. No commission, no brokerage. Never on both sides of the same project.
Confidentiality agreement before any document. Professional liability insurance. Best-efforts obligation: only RTE and Enedis commit to capacity and a date.
FREQUENTLY ASKED QUESTIONS
Are my answers stored?
No. The calculation runs in your browser. Only the form, if you choose to send it, passes the result to us.