In France, AI campus announcements are counted in gigawatts. Grid capacity reserved at RTE by data center projects has reached 21 GW, while the France Datacenter-EY barometer projects 2.8 GW installed in 2030. Between announcement and energisation come the grid connection, permits, public consultation and construction.

This tracker brings together, for the main public projects, what has been announced and what has actually been secured to date. It does not rate projects or make forecasts: it simply separates announced, authorised and energised.

PROJECTS TRACKED

Status as of 17 November 2026. Scroll the table horizontally on mobile.

ProjectDeveloperAnnounced capacityGrid connection (public)PermitsIn serviceStatusSources
AI campus, Fouju (Seine-et-Marne)MGX, Bpifrance, Nvidia, Mistral AI1.4 GWNot detailed publiclyTwo appeals announced (Melun administrative court, Paris appeal court)No known energisationIn litigationNational press
Ozans zone, Étrechet (Indre)Google120 MW first phase (225 kV), 500 MW to 1.2 GW over time per the press225 kV connection, then RTE 400 kV worksCNDP consultation opened 9/11/2026; Engie energy MoU (13/11/2026)None; first building around 2030 per the pressIn consultationLa Nouvelle République; Engie-Google release; DCmag
Le Bosquel (Somme)SoftBank Group and SesterceUp to 1.4 GWNot detailed publiclyCNDP consultation 2/11 to 18/12/2026None; energisation targeted in 2031In consultationPicardieWeb; France 3
e-Valley, Cambrai-Épinoy (Nord)Data4 (Brookfield)Up to 1 GW, at least 300 MW near termFirst step at MV: 29 km of grid, works scheduled for 2027Land sale approved by the local authorityNone; first energisation considered for 2027Announced2025 announcements; April 2026 tender
Former Bridgestone plant, Béthune (Pas-de-Calais)Azur Datacenter (tenant: Nebius)240 MW in three phasesAbout 45 MW available at start; final connection about three years away per the press—First phase delivered according to Azur DatacenterIn service (partial)Azur Datacenter; La Voix du Nord
Paris-Villaroche business zone, Réau (Seine-et-Marne)Verne (Ardian group)500 MW targeted, 250 MW by 2030Presented as secured by the developerConsultation closed 3/11/2026; permit planned early 2027NoneIn consultationChoose France; DCmag; actu.fr
Former Stellantis site, Trappes-Élancourt (Yvelines)Goodman300 MW (3 data centers)Not detailed publiclyConsultation ended 1/09/2026; public inquiry to comeNoneIn consultationLes Echos; DCmag
Former plant, Rantigny (Oise)Rantigny Data Center300 MW targeted in 2029Not detailed publiclyFavourable inquiry opinion with eight reservations (09/2026); neighbouring Cauffry council voted against (16/11/2026)NonePermittingPublic inquiry file; Oise Hebdo
Villefontaine and Eybens (Isère)DataOne400 MW combined targetedNot detailed publiclyNo permit decision reportedNone knownAnnouncedSolutions Numériques
Cézanne, Les Pennes-Mirabeau (Bouches-du-Rhône)Telehouse (KDDI)48 MW commercial, 70 MW requested from RTERequest to RTE per the pressAppeals against the building permit and operating authorisationNoneIn litigationNext; regional press
Rovaltain, Alixan (Drôme)SesterceNot stated hereNot detailed publiclyPermit suspended July 2026; appeal announcedNoneIn litigationGrenoble administrative court; DCmag
Wissous (Essonne)CyrusOneUp to 60 MW in three phasesNot detailed publiclyAppeal rejected by Versailles appeal court (04/2026)Not knownAuthorisedAFP

WHAT THE TABLE SHOWS

Of the twelve projects tracked, only one reports a first phase in service, with only part of its capacity available from the grid at start. The others are in consultation, permitting or litigation. Announced capacity adds up in gigawatts; capacity in service is so far counted in tens of megawatts.

This says nothing about project quality: a campus of this size takes several years, and France remains one of the European countries where a large-scale connection is achievable within reasonable timeframes. But for an investor, lender or supplier, the right question is not "how many MW announced?" but "which step has actually been cleared?".

OUR METHOD

Tracker rules Public information only, with its source
Figures are those announced by developers or reported by the press; we do not recalculate them
"None" in service means no energisation has been publicly announced, not that no work has started
Updated every quarter, and whenever a correction is reported

Right of reply and correction. Do you lead one of these projects, or have more recent public information? Let us know: we check and correct quickly, citing the source.

See also our consultations, permits and appeals tracker, our page on queue position at RTE and our site tracking for investors.

FREQUENTLY ASKED QUESTIONS

How many AI data centers are in service in France?

Among the large campuses announced since 2025, very few have announced energisation, and always partial. France's installed base was about 0.9 GW in 2025 according to France Datacenter and EY-Parthenon, across all generations of data centers.

Why does announced capacity differ so much from capacity in service?

A campus of several hundred megawatts is built in phases, and each phase depends on the grid connection, permits and delivery of high-voltage equipment. Announced capacity is a long-term target.

How do I request a correction?

Use the "Report a correction" button and give the public source. We update the table after checking.

NEXT STEP

Holding an exploratory study, a PTF or a connection agreement? We review it independently before you sign or invest, or prepare the PTF request with you. The expert: Xavier Watrelos.

Have a document reviewed · Prepare a PTF request

THE GRIDREADINESS MONTHLY LETTER

Grid connection, equipment and data center projects in France: what matters, once a month.

Your email is used only for this letter. Legal notice.

Thank you, you are subscribed.

Sending failed. Email fred@gridreadiness.com.