In France, AI campus announcements are counted in gigawatts. Grid capacity reserved at RTE by data center projects has reached 21 GW, while the France Datacenter-EY barometer projects 2.8 GW installed in 2030. Between announcement and energisation come the grid connection, permits, public consultation and construction.
This tracker brings together, for the main public projects, what has been announced and what has actually been secured to date. It does not rate projects or make forecasts: it simply separates announced, authorised and energised.
PROJECTS TRACKED
Status as of 17 November 2026. Scroll the table horizontally on mobile.
| Project | Developer | Announced capacity | Grid connection (public) | Permits | In service | Status | Sources |
|---|---|---|---|---|---|---|---|
| AI campus, Fouju (Seine-et-Marne) | MGX, Bpifrance, Nvidia, Mistral AI | 1.4 GW | Not detailed publicly | Two appeals announced (Melun administrative court, Paris appeal court) | No known energisation | In litigation | National press |
| Ozans zone, Étrechet (Indre) | 120 MW first phase (225 kV), 500 MW to 1.2 GW over time per the press | 225 kV connection, then RTE 400 kV works | CNDP consultation opened 9/11/2026; Engie energy MoU (13/11/2026) | None; first building around 2030 per the press | In consultation | La Nouvelle République; Engie-Google release; DCmag | |
| Le Bosquel (Somme) | SoftBank Group and Sesterce | Up to 1.4 GW | Not detailed publicly | CNDP consultation 2/11 to 18/12/2026 | None; energisation targeted in 2031 | In consultation | PicardieWeb; France 3 |
| e-Valley, Cambrai-Épinoy (Nord) | Data4 (Brookfield) | Up to 1 GW, at least 300 MW near term | First step at MV: 29 km of grid, works scheduled for 2027 | Land sale approved by the local authority | None; first energisation considered for 2027 | Announced | 2025 announcements; April 2026 tender |
| Former Bridgestone plant, Béthune (Pas-de-Calais) | Azur Datacenter (tenant: Nebius) | 240 MW in three phases | About 45 MW available at start; final connection about three years away per the press | — | First phase delivered according to Azur Datacenter | In service (partial) | Azur Datacenter; La Voix du Nord |
| Paris-Villaroche business zone, Réau (Seine-et-Marne) | Verne (Ardian group) | 500 MW targeted, 250 MW by 2030 | Presented as secured by the developer | Consultation closed 3/11/2026; permit planned early 2027 | None | In consultation | Choose France; DCmag; actu.fr |
| Former Stellantis site, Trappes-Élancourt (Yvelines) | Goodman | 300 MW (3 data centers) | Not detailed publicly | Consultation ended 1/09/2026; public inquiry to come | None | In consultation | Les Echos; DCmag |
| Former plant, Rantigny (Oise) | Rantigny Data Center | 300 MW targeted in 2029 | Not detailed publicly | Favourable inquiry opinion with eight reservations (09/2026); neighbouring Cauffry council voted against (16/11/2026) | None | Permitting | Public inquiry file; Oise Hebdo |
| Villefontaine and Eybens (Isère) | DataOne | 400 MW combined targeted | Not detailed publicly | No permit decision reported | None known | Announced | Solutions Numériques |
| Cézanne, Les Pennes-Mirabeau (Bouches-du-Rhône) | Telehouse (KDDI) | 48 MW commercial, 70 MW requested from RTE | Request to RTE per the press | Appeals against the building permit and operating authorisation | None | In litigation | Next; regional press |
| Rovaltain, Alixan (Drôme) | Sesterce | Not stated here | Not detailed publicly | Permit suspended July 2026; appeal announced | None | In litigation | Grenoble administrative court; DCmag |
| Wissous (Essonne) | CyrusOne | Up to 60 MW in three phases | Not detailed publicly | Appeal rejected by Versailles appeal court (04/2026) | Not known | Authorised | AFP |
WHAT THE TABLE SHOWS
Of the twelve projects tracked, only one reports a first phase in service, with only part of its capacity available from the grid at start. The others are in consultation, permitting or litigation. Announced capacity adds up in gigawatts; capacity in service is so far counted in tens of megawatts.
This says nothing about project quality: a campus of this size takes several years, and France remains one of the European countries where a large-scale connection is achievable within reasonable timeframes. But for an investor, lender or supplier, the right question is not "how many MW announced?" but "which step has actually been cleared?".
OUR METHOD
Figures are those announced by developers or reported by the press; we do not recalculate them
"None" in service means no energisation has been publicly announced, not that no work has started
Updated every quarter, and whenever a correction is reported
Right of reply and correction. Do you lead one of these projects, or have more recent public information? Let us know: we check and correct quickly, citing the source.
See also our consultations, permits and appeals tracker, our page on queue position at RTE and our site tracking for investors.
FREQUENTLY ASKED QUESTIONS
How many AI data centers are in service in France?
Among the large campuses announced since 2025, very few have announced energisation, and always partial. France's installed base was about 0.9 GW in 2025 according to France Datacenter and EY-Parthenon, across all generations of data centers.
Why does announced capacity differ so much from capacity in service?
A campus of several hundred megawatts is built in phases, and each phase depends on the grid connection, permits and delivery of high-voltage equipment. Announced capacity is a long-term target.
How do I request a correction?
Use the "Report a correction" button and give the public source. We update the table after checking.
NEXT STEP
Holding an exploratory study, a PTF or a connection agreement? We review it independently before you sign or invest, or prepare the PTF request with you. The expert: Xavier Watrelos.
THE GRIDREADINESS MONTHLY LETTER
Grid connection, equipment and data center projects in France: what matters, once a month.
Your email is used only for this letter. Legal notice.
Thank you, you are subscribed.
Sending failed. Email fred@gridreadiness.com.