"Will a data center take our water?" It is one of the first questions asked at public meetings. The answer depends less on national figures than on three local factors: the cooling technology, where the water comes from, and the state of the resource at the project's location.

DOES YOUR SITUATION LOOK LIKE ONE OF THESE?

Francis GillardFrancis Gillard
Data center design & audits
Blandine CazellesBlandine Cazelles
Crisis communication & public affairs
All situations →

1. HOW MUCH WATER DATA CENTERS USE IN FRANCE

Arcep figures (2024 data, published May 2026) 575,000 m³ of water withdrawn by data centers, almost entirely drinking water
A volume back close to its 2022 level, after an exceptional rise in 2023 linked to works on older sites
Electricity consumption of data center operators up 12% over the year

At national level, this volume is modest. But a national average says nothing about a given site: a large data center cooled by evaporation, on a resource already under pressure in summer, can matter locally. That is the point local authorities and residents are right to check.

2. THE RULES THAT APPLY

If the site is supplied by the public drinking water network, as most are, the issue is first settled with the water utility: network capacity, the supply contract, and compliance with restrictions set by the prefect during droughts.

If the site draws water itself from an aquifer or a river, French water law applies. Below 1,000 m³ a year, the withdrawal counts as domestic use. Above that, the nomenclature sets the thresholds:

Water law thresholds Groundwater: declaration above 10,000 m³ a year, authorisation from 200,000 m³ a year
Rivers and connected aquifers: declaration from 400 to 1,000 m³ an hour (or 2 to 5% of the flow), authorisation above

Evaporative cooling towers also fall under the classified installations regime, in particular for legionella prevention.

Building permits. Law no. 2026-403 of 26 May 2026 allows the authorities to refuse the building permit of a data center located in an area with "structural tensions on water resources". It is an option, not a ban, and the law does not define the notion. The Conseil d'État had already accepted, in December 2025, that a mayor may refuse a permit on grounds of insufficient water resources.

Transparency. Data centers above 500 kW already report their water consumption to the EU database, with their other indicators. See the EU data centre rating.

3. WHAT DRIVES CONSUMPTION

Dry coolers and closed loops use very little water but more electricity. Adiabatic or evaporative systems save electricity but use water, especially during heatwaves, when the resource is scarcest. The choice is a trade-off between water and power, which should be explained, quantified and owned.

4. A FREQUENT QUESTION: "INDIRECT" WATER

Power generation, nuclear in particular, also withdraws and evaporates water. It is not counted in data centers' reported consumption. Some argue it should be included in their footprint; others point out that this water produces electricity for every use, and that allocating it to data centers alone raises methodological questions. The debate is legitimate; it benefits from sourced figures.

5. WHAT TO ASK A PROJECT DEVELOPER

For local authorities, residents and lenders How much water a year, and above all at peak, in midsummer?
Where does the water come from: public network, borehole, river?
Which cooling technology, and why?
What happens under a drought order: can the site run without water?
Will water be reused, and waste heat recovered?
Will actual consumption be published every year?

A project that answers these questions clearly before public consultation avoids most disputes on the subject. See also cooling with quarry and mine water.

Sources: Arcep, annual survey "Pour un numérique soutenable", 2026 edition (2024 data), 21 May 2026; Law no. 2026-403 of 26 May 2026, article 35, and commentaries by Gossement Avocats and Kohen Avocats; French water law nomenclature (headings 1.1.2.0 and 1.2.1.0). This article is general information, not legal advice.

FREQUENTLY ASKED QUESTIONS

How much water do data centers use in France?

According to Arcep, data centers withdrew 575,000 m³ of water in 2024, almost entirely drinking water. A site's local volume depends mainly on its cooling technology.

Do French water law rules apply to data centers?

Yes, if the site draws water itself from an aquifer or a river above the nomenclature thresholds: declaration above 10,000 m³ a year from groundwater, authorisation from 200,000 m³ a year. If it is supplied by the public network, the issue is settled with the water utility.

Can a data center be refused for lack of water?

Yes. The law of 26 May 2026 allows the authorities to refuse the building permit of a data center in an area with structural tensions on water resources. It is an option for the authorities, not an automatic ban.