A data center never stops. Running it 24/7 takes a team that is properly sized, organised in shifts, trained before commissioning and able to last. With the shortage of cooling and electrical technicians, a team hired too late or poorly organised becomes an operating risk.
HOW MANY PEOPLE TO COVER ONE 24/7 POST?
A post staffed continuously represents 8,760 hours a year. A full-time employee in France works about 1,600 hours a year. So it takes about 5.5 people to cover a single post around the clock, before leave, training and absences.
| Permanent on-site presence | Shift headcount needed (order of magnitude) |
|---|---|
| 1 technician around the clock | 5 to 6 people |
| 1 HVAC technician + 1 electrician around the clock | 11 to 12 people |
| 1 shift lead + 2 technicians around the clock | 16 to 18 people |
IN-HOUSE, CONTRACTOR OR MIXED
| Model | Strengths | Watch points |
|---|---|---|
| In-house team | Deep site knowledge, control of skills, retention possible | Hard hiring, fixed cost, replacing leavers |
| Integrated maintenance contract | Fast mobilisation, cover by the contractor, predictable cost | Contractor staff turnover, variable quality, dependency |
| Mixed model | In-house shift leads and managers, outsourced technicians and specialists | Interfaces and responsibilities must be written precisely |
TIMELINE BEFORE COMMISSIONING
OUR ASSIGNMENT: OPERATIONAL READINESS
With network experts who have designed, commissioned and operated data centers, we prepare team sizing and shift patterns, job descriptions and hiring timeline, the in-house versus contractor choice and maintenance specification, the training plan and the operating procedures. Hiring of technicians stays with the operator or its contractors. See also expert staffing for long assignments.
FREQUENTLY ASKED QUESTIONS
How many people does it take to run a data center 24/7?
About 5.5 people to cover one post around the clock, before absences and training. The total depends on how many posts are permanently staffed, the day team and what is outsourced.
When should the operations team of a new data center be hired?
Managers about nine months before commissioning and technicians about six months before, so they take part in commissioning tests.